Dear Friends,
We are dealing with typical subcontracting requirement, I have all the master data in place for the setup.
After planning run, I am getting Preq at manufacting plant, against which orders are getting created at subcon location and requirement for components are getting created, but the preqs are not getting created at subcon location against manufacturing plant.
I have defined Planning Procedure as 3 i.e Cover Dependent Requirements Immediately.
Still system not creating any Preqs in order to cover subreqs.
Anything sugestions?
Hi,
The system will not create PurReq for SubReq at the Subcon location. It will create Stock transfer Reservations. Please verify T-lane for the components exist between Plant to Subcontracting location.
Regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Please check if you have the transporation lane from manufacting plant to subcontracting location. You must maintain the means of transport for the transportation lane, and the component should be assigned to it.
For more information please check
http://help.sap.com/saphelp_scm70/helpdata/EN/71/78573da974c729e10000000a11402f/content.htm
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
13 | |
4 | |
3 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.