Hi Experts,
For some reason our system stopped generating "corrected history" KF.
1. It is defined in planning area -> extras -> forecast settings.
2. Statistical forecast generation job has "lifecycle planning" active.
3. "Read corrected history data from planning version" is unticked.
Do you know what can be the reason? Have you meet such thing?
Thanks.
Hi,
I request you to reduce the number of periods(or number of months or weeks in start date and end date) for forecast horizon and history horizon in //mc96b for your master forecast profile and re-test your issue. Let the total of both periods be less than 50.
Thanks and Regards,
Nithin.