Hi,

In the t-code CJ31 to display budget, the assigned budget column is displayed for some WBS and not displayed for some. Please help on when this column will be displayed in CJ31.

Regards,

Immanuel.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Try to find out the business transactions that were carried out for the respective WBS elements. Create a test project and at different stages check when the value gets populated in the Assigned column. You should be able to find it out.

Regards,

Gokul

Former Member
0 Kudos

Hi Gokul,

Thanks for the reply. Actually for the same WBS if i open it in Change mode in CJ30 and make any change it is displaying the Assigned Budget column. But it is not displaying in CJ31. For this WBS the budget is already exceeded and there is no Availablity check activated. Is there any chance that this is the reason.

Regards,

Immanuel.

Former Member
0 Kudos

Hi Gokul,

I have added more budget to the WBS and activated the availability control and CJ31 is displaying the assigned budget column.

Thank you.

Regards,

Immanuel.

Former Member
0 Kudos

u2018Assigned Valueu2019 is Residual Plan + Actuals + Commitment. Do you have any of this against your WBS?