on 08-30-2011 10:50 PM
Friends,
we got some mitigating controls popped up in controls library option under management view, but those are actually active and i suspect this is happening because of not mentioning valid to date when they are created and mitigating controls gets expired after 365 days(as per our setting).
Is there any way that these can be reactivated or do we need to delete and re-create them.
Thanks for the help in advance.
Hi Srinu,
Mitigation controls will never get inactivated. It is the users who will be out of the mitigation controls after 1 year (default mitigation period).
However, if you are referring to the Active and Inactive controls in the management view under the control library, the Inactive controls are the one which are untouched from a long time. If you mitigate another user, it will be automatically added in the active control list.
Hope this helps!!
Regards,
Raghu
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The management reports will be updated only when you run the full sync jobs (you can see an option to update the management reports in the schedule jobs screen). Since you have assigned an user now, schedule the full sync jobs and you will see the updated list of active/inactive mitigation controls now.
Regards,
Raghu
Edited by: Raghu Boddu on Sep 4, 2011 3:43 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.