Schedule Lines and Goods Issue Dates

0 Kudos

Hi Gurus,

I am trying to write a report which will show all the planned goods issue dates for orders. Question : when a delivery document is created and it has a different planned goods issue date than an existing schedule line, will a new schedule line be created or copied into or will nothing happen. I guess what I am trying to ask is can I just go read the schedule line or I must go into delivery document to get the latest planned goods issue date.

Thanks.

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi,

Yes you need to refer LIKP for the planned GI date--I think you're trying to improve the performance but LIKP should be the source.

Regards

Raghu.

Former Member
0 Kudos

Hi,

Actually requested delivery date & schedule ling date are different & at the time of creation of outbound delivery, it considers requested delivery date to create outbound delivery & not a schedule line date.

Hope this will help you