Hi,
When I go to the DP planning area it let me create new ratios, but the SNP planning area does not le t me create them. What should I do?
What is the best way to simulate scenarios in SNP?
- One Planning area with two versions? Or two planning areas?
Thanks a lot
The best way is to have multiple versions for simulation.
SNP reads live cache data and hence you can also use multiple planning area.
Vipul