on 08-29-2011 6:35 AM
Dear All,
I am facing problem in delivery. In my case scenario is-
1. There are 10 materials with 20 quantities.
2. I create a sales order only for two material with 5 quantities and enter wbs element number.
Now when i use CNS0, enter sales order number and wbs elelment number system shows all 10 materials that I dont want means I want the materials that are included in sales order. Please help me how to control this.
Please read SAP Help for a better under standing...
I mentioned below a line from SAP help for your info.
...... it selects material components, the system takes components into account that have been assigned to either a network or ...... ...
Please follow the below path to access the help..
SAP Help Portal >>> Logistics >>>> Project System >>> Material >>>> Delivery from Projects......
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.