Hi,
A sales order with material and assign WBS can display the plan revenue which equal sales revenue. How can I make the material cost also be display as plan cost? This material cost should equal standard price of material master.
It is not possible to copy material cost from sales order to project. Please activate network cost planning, and assign the same material in the project structure, so system will take the material cost in plan cost.