I have gone through all the threads related to CJIF. I have not got right solution.
I have business scenario in PS - Customer Projects with billing element.
1. project creation + network creation
2. project budgeting & releasing
3. Project pr-po & procurement of materials & services
4. based on Project Teco status : Sales Order raising for Materials & Services
5. PRoject - PSG settlement carried against Sales ORder number
we are not using milestone billing or billing plan & we have not configured any result anaysis version.
after the above, now when i am running CJIF for the above related projects, i am not getting any values
pl help in getting the output
Thanks in advance
Srihari
Hi,
Are you running RA? CJIF displays RA line items.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.