on 08-25-2011 11:47 AM
Hi Gurus,
could you please let me know if any customization is needed for the item Timeline Monitor graphic functionality?
I'll explain the issue:
I create an item, insert Planned and Forecasted start/finish date for the item and for its decision points and when I press button 'Timeline Monitor' I'm getting the following error messages:
'Mapping for field names does not exist'
and
' Customizing is missing'
Going through the SAP customizing menu the only thing I found is a BAdI 'Timeline monitor'.
I forgot to mention that I'm using PPM 5.0 version.
Please help!!
Many thanks in advance.
Regards
Edited by: Accenture Consultant Accenture Consultant on Aug 25, 2011 1:44 PM
Hello,
please check table INM_OF_FCAT. it the table is empty thats the reason for your problem.
you can maintain the table via view V_INM_OF_FCAT or copy the customizing from the 00 client
(use transaction /RPM/CUST_COPY to copy the customizing of this table.
The timeline monitor should work if the table is maintained.
Best Regards
Isabella
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi,
I hope you have maintained DP - phase or DP-WBS assignments and dates are as per synchronisation.
I am not sure why you are getting the error beacuse with above settings it should not create any problem.
Pramod
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
First of all, thanks for your reply.
I think we have that customizing correctly done:
In the item type settings we've defined the 'Link to Project System' = Portfolio and Project Management. Also we have mapped the item type to the project template we are using (SAP Portfolio and Project Management > Portfolio Management > Global Customizing > Portfolio-Independent Settings > Map Item Type to Project or PS).
In SAP Portfolio and Project Management > Common Functions > Decision Flow Management Settings > Attribute Synchronization
we have defined horizontal and initial creation synchronization scenarios and have mapped Item-Project and item Decision points-Project Phases dates.
Is there anything else required?
We are having several issues with item and project synchronization, so I suspect that there might be our problem with this Timeline Monitor graphic too if no other customization is required for it.
Any other idea?
Regards
User | Count |
---|---|
3 | |
3 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.