SRM7.0 Service Confirmation Cancellation not posting in ECC

Former Member
0 Kudos

Hi Experts ,

We have SRM7.0 with ECC6 ( Ehp4) having Classic Scenario . We have No workflow in SRM for any document. ( Auto approval)

When we post Confirmation ( Service Entry Sheet) of Service PO in SRM, it immidialty Post the Mat Doc and Service Entry Sheet in PO in ECC ( in PO history tab)a nd updated back in SRM SC & Confirmation Doc. No issues.

But, when we cancel/revrese this Confirmation Document in SRM, it do not post Material Document in ECC PO for this reversal ( Rejection of Service Entry Sheet) and the Status of this Cancel Confirmation Doc remains "HEADER I1017 Currently Being Transferred".

I run the update job, pushed Confirmation Manully by FM BBP_PD_CONF_TRANSFER_V2 in SRM..but no use..

For Confirmation of material I know there is IDoc Message MBGMCR, but for Confirmation Service I don't see any IDoc. How it transfers to ECC then ?

Can anyone please suggest me what should be issue a nd how to resolve it ?

Thanks

NaP

Accepted Solutions (0)

Answers (2)

Answers (2)

former_member311502
Discoverer
0 Kudos

Hello,

We face the some issue , did you find a solution?

thanks in advance

Best regards

Former Member
0 Kudos

Issue resolved by applying the Note 1529106 - Cancellation of service confirmation not posted to backend