Budget control for Contracts

Former Member
0 Kudos

Dear All,

I want to know , whether we can have budget checks for contracts.

Regards,

VIshal

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

No budget check at contracts level in standard SAP.

Regards,

Harsh.

Former Member
0 Kudos

Dear Vishal,

We need your reply on this. Are you refering any sales contract budget.

If you are refering it is a project, other answers are holds good and you can close the thread.

Regards

N.Raju

Former Member
0 Kudos

Hi Narayan,

I am referring to contracts created under project and not Sales contracts.

As per the suggestions received , I think no standard configuration is there for budget check at contract level in a Project.

Still i would like to know , if there is any solution to check budget at contact level

Regards,

Vishal

former_member203108
Active Contributor
0 Kudos

Commitments are not created while creating contracts, so there wont be any budget checks for that.

Former Member
0 Kudos

Dear All,

Thanks for the support.

I am closing this thread.

Regards,

Vishal

Former Member
0 Kudos

Hi,

In PS, Budgeting is done only for the WBS Elements. You can use availability control by assigning orders to WBS Elements.

Regards

Sagar

Former Member
0 Kudos

Hi,

Let us know what is meant by contracts. R u refering SD -Contracts?.

In PS, Budget check is possible on WBS Elements.

Regards

N.Raju

Former Member
0 Kudos

Hi Narayan,

R u refering SD -Contracts?.

Appreciate your participation in the forum but please do not use SMS language here.

Regards,

Gokul