on 08-24-2011 12:57 PM
Dear All,
I want to know , whether we can have budget checks for contracts.
Regards,
VIshal
Hi,
No budget check at contracts level in standard SAP.
Regards,
Harsh.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Narayan,
I am referring to contracts created under project and not Sales contracts.
As per the suggestions received , I think no standard configuration is there for budget check at contract level in a Project.
Still i would like to know , if there is any solution to check budget at contact level
Regards,
Vishal
Hi,
In PS, Budgeting is done only for the WBS Elements. You can use availability control by assigning orders to WBS Elements.
Regards
Sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Let us know what is meant by contracts. R u refering SD -Contracts?.
In PS, Budget check is possible on WBS Elements.
Regards
N.Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |