Dear All ,
I am SD consultant and wants to know
1. Can We assign material to a WBS ?
2. Can we assign a WBS to material ?
How and what are the prerequisites for the both the option ?
Regards Pooja
Hi,
A material can be assigned to an activity as a material component and an activity can be assigned to a WBS Element. That is there general flow.
Orders like purchase orders, sales orders etc can be assigned to WBS Elements.
Regards
Sagar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You can assign materials to a WBS by using easy cost planning.
I don t get the point of assigning a wbs to a material, i don t think you can.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
Please explain what did you mean by assign?
Is it attaching material componnets to WBS or tranfere materials to WBS.
Material tranfering to WBS(project stocks ) is possible via transferpostings movements like 415
hope this would help.
regards,
SL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
1. Can We assign material to a WBS ?
No.
2. Can we assign a WBS to material ?
No
You can neither assign a material to a WBS nor assign a WBS to a material. You can assign material only to an activity in the project structure. However you can account assign the WBS to a purchase order or a sales order.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.