WBS is closed status , but balance is not 0 ?

Former Member
0 Kudos

Dear Expert,

We have one project , which WBS is close status, but when I check the balance via CJI3, the balance is not 0.

What we don't understand is , if the balance is not 0 , how this WBS can be closed. Normally , when we try to close the WBS, there is one error message to say the balance is not 0 ...

Where is the problem ? what I should check ?

Best REgards

Shubin

Accepted Solutions (1)

Accepted Solutions (1)

former_member230675
Active Contributor
0 Kudos

normally it wont allow. please check the variant you are using in CJI3 may be some filter is set and it is filtering settled values.

Former Member
0 Kudos

Hi Abdul,

I just checked in CJI3, there is no filter . Do you know something else I should check ?

BR , Shubin

Former Member
0 Kudos

Hi,

yes it is possible.

Check the settlement profile settings; there are 3 settings as;

1. to be settled in full

2. can be settled

3. not for settlement

If the setting is at 2nd or 3rd the object can be closed without having balance zero.

Regards,

Harsh.

Former Member
0 Kudos

Hi Harsh,

thanks a lot , the problem is solved.

BR ,shubin

Answers (1)

Answers (1)

Brendan_Ward
Advisor
Advisor
0 Kudos

Hello Shubin,

It is possible there is an inconsistency. Follow the steps below to repair:

1) Run report RKANBU01 for the project to correct the COOI table first.

2) After running the report, run report RKACOR04 from SAP Note 21649 for the project.

3) Then run transaction CJEN for the project. THIS IS IMPORTANT as the project database needs to be updated.

You can check if commitments still exist on an object with either report CJI5 or report RKACSHOW and checking table

COOI. See SAP Note 152571 for further information.

Regards,

Brendan