dear

In notification i need to assign QM order (QN01) for the purpose of con confirmation cost ...

But i am not able to assign QM order,,While i click the order in notification system show a error message as

=========================

The function you selected

cannot be

carried out:

Assign order

=====================

pls tell me what are the config i need to check

i have already done in following location

QCC0>NOTIFICATION>PROCESSING>DEFINE COSTING PARAMETER>ACCOUNT ASSIGMENT OF QM ORDER

FAISAL

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

for Order type QN01 in said path in customization if you have assigned

Notifictn type F2 to Plant combination

and

Business Area & Cost Center & CO Area

then system creates the Order for notification which can be seen in notification under processing tab

muhamed_faisal
Active Participant
0 Kudos

Yes sujit after giving business area it is working

But is it compulsory to assign material documnet number?

I try without assigning material documnet number ...it is not working

Which is the standard proccuder?

Faisal

Former Member
0 Kudos

There has to be some reference number ,not necesserilly Material document.Its may be purchse order or production order etc.