Hi everyone!

We are implementing Results Analysis for projects. But the client is asking if there is a way to exclude some cost elements of the results analysis calculation. We are using method 07, POC based in the project milestones.

This is why they need this. They say that very often they they have costs higher to what they should be according to the month's billing. So they need to send the corresponding part to a WIP account. But not all the costs. They have internal costs (like the hours of internal resources) and external costs (like materials procurement or external services contracts). They only want to send to WIP the exceeding external costs. But leave all the internal costs in a cost account. So to do this we need to exclude these kind of cost elements (secondary cost elements) from the results analysis calculation. Is there any way to do this? Any ideas?

Thanks in advance!

Regards,

Thalos.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

In OKG4, next to Line ID there is a field where you can set "N" which means not to include. Make this settinng for required cost elements / Line ID's and then test the changes.

Regards

Sreekanth

federico_gregoret
Participant
0 Kudos

Thanks Sreekanth!!

We did it this way and it worked!!

Thanks for your help!

Regards, Thalos.