I have a requirement for a report in SRM which should update the account assignment in SRM-PO with the new WBS Element / Fund. Now, I am little new to SRM programming. Could some one give me detailed steps as to what FMs do I need to use and how do I go about updating the PO in SRM?
Thanks,
Venkata Phani Prasad K
Hi,
You can use the function BBP_PD_PO_UPDATE to update the PO. Remember to call BBP_PD_PO_SAVE anc COMMIT WORK after calling update function.