on 08-22-2011 11:47 AM
Dear Expert,
Here i am creating Purchase Requisition from the project by assigning
material component in Network Activity. All the Material assigned to a
single network have a single Purchase Requisition with different
different Line Item which is acceptable but once the Purchase Order
created and released and a new material component is assigned to the same
network. Now it will added into the same purchase requisition with
separate line item, which is not acceptable since that purchase
requisition was already closed and Purchase Order was released then
system should generate a new Purchase Requisition against the same
Network,
Pls suggest how it could be configure, is there is any setting in config
to full fill this requirement.
Hi,
As such there is no config requirement.
Its purely your process needs to be re think.
You are assigning the material to activity and getting PR,PR,GR and all . Once the material is consumed, thinking that activity is also over. In this case, again you are assigning other material to the same activity and you want to have the different purchase requistion not same PR with line item.
option 1, you can have the different PR nos always whenever you are assigning the materials to same activity. If 1 activity requires, 10 materials, you will have 10 PR's which is practically not correct. chnages you can do it in parameter for network type.
Option 2, New materials which is required can have a new network.
Regards
N.Raju
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.