Task Percent Complete and Actual Dates - RELATE TO STATUS

Former Member
0 Kudos

Hi,

We are on PPM 5.0.

For Project Management (cProjects), we have a requirement whereby task status should not be set to 'Complete' unless:

1. The Percent Complete is 100%

2. The Actual Start and Actual Finish dates have been entered.

Is it possible to realize this?

Please advise.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

%age completion is independent of the status of the task as per standard SAP PPM 5.0. You'll need to use BADIs in order to meet you requirement.

---

Gautam

Former Member
0 Kudos

Hi Deepak,

As per my understanding, in standard it is not possible.

Thanks

mariano_sabiche
Active Participant
0 Kudos

Hello Deepak;

Yes it's posible with an enhacement!!

Best regards.

Mariano