on 08-22-2011 8:50 AM
Hi,
We are on PPM 5.0.
For Project Management (cProjects), we have a requirement whereby task status should not be set to 'Complete' unless:
1. The Percent Complete is 100%
2. The Actual Start and Actual Finish dates have been entered.
Is it possible to realize this?
Please advise.
Hi,
%age completion is independent of the status of the task as per standard SAP PPM 5.0. You'll need to use BADIs in order to meet you requirement.
---
Gautam
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Deepak,
As per my understanding, in standard it is not possible.
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Deepak;
Yes it's posible with an enhacement!!
Best regards.
Mariano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
10 | |
5 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.