Please let me kno the function of foloowing field in SPRO-QM-Maintain setting at plant level-result recording-
Proposol for inspection point valuation
Plant selected set
Code Code group
where these are used in result recording.
Proposol for inspection point valuation
Plant selected set
Code Code group
where these are used in result recording.
This is used with reference to inspection point valuation.( inspection point you define at the Inspection plan header)
In QCC0->quality planning->inspection planning->general->define identifiers for inspection point--->for a Inspection point
you do not define any valuation here then valuation defined in the plant level will be considered.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
hi surjit,
I know inspection points are assigned in inspectio plan header,
My question is about SPRO settings, please check following flow and tell where in result recording Proposol for inspection points valuation used.
SPRO-QM-Basic settings-Maitan settings at plant leve-then selected a particular plant- and double clicked-result recording-
Proposol for inspection points valuation
plant Selected set
code Code group
You did not read my thread carefully if you do not define anything in customization
In QCC0->quality planning->inspection planning->general->define identifiers for inspection point--->for a Inspection point
then the plant level setting is consdiered as defualt on.that is a reason we define valuation at plant level setting also.
Once the result recording is done system ask for valuation depending upon the defination of inspection point.
the selected set defined at the plant level is used for valuation of inspection point.