I would like to know if there is a way to allow CTM to create planned orders early only to prevent lateness and eliminate planned order early due to resource being available?
Currently we have a CTM IMG setting that allows 30 days earliness. This causes planned orders to get created early if supply and resource are available even if we could be just in time and fulfill demand.
In other words, I would like CTM to plan early demand fulfillment only we we would be late to demand date else ontime fulfillment.
Hi,
May I know, what is the planning direction you maintained? If it is Forward scheduling, then this will happen. Please change it to Backward scheduling and try. The main aim of the maximum earliness is to avoid storage costs. At any cost, CTM will not schedule if there is no resource or supply availability to avoid the lateness.
Regards,
Manimaran M.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
9 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.