on 08-19-2011 2:54 PM
Hi All,
The PO Dates in APO (Product view) and R/3 Stock Requirements list are
not matching.
For example for material X you will see that the dates in
are 6 months earlier in MD04 than in APO.
I reviewed note 333386 and found that we were in compliance with this
note.
Any ideas on what could be causing these inconsistencies.
Regards,
Rumi
Hi,
Other than above suggestions, you can also check /sapapo/cq for any CIF queues error.
Regards!
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rumi,
As Claire has said, please see if there is any inconsistency for said product location in /SAPAPO/CCR.
If you do not see any inconsistency in this report. You can also see inconsistencies in post processing records with report
/SAPAPO/CPP.
Also, see whether you have any blocked queues from ECC and APO side.
Regards,
Abhay Kapase
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Please check if /SAPAPO/CCR can correct such inconsistency or not.
In most cases such inconsistency is caused by user exits. Please check your user exits if you have.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
7 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.