on 08-19-2011 7:58 AM
Hi All,
How can we check that a PR has been created manually (i.e TCode ME51N) or through Projects (i.e TCode CJ20N)?
Please guide.
Regards,
Nitisha
Hi,
Simplest way to check is if the material component is attached to an activity in the project. You will be able to see the PR number there in case the PR is generated from project. If the PR is created manually through ME51N you won't see the material component attched in the project.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks All...
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Assuming that project through PR use standard document type "NB" system would create PR numbers different to ME51N.
also when u open PR on me52n PR document type would show on left side of PR number.
Standard SAP project PR it is always "NB" if modifcation is not done
regards,
SL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
92 | |
11 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.