on 08-19-2011 4:34 AM
In the Report S_ALR_87013533 Costs: Plan/Actual/Commitment/Rem.Plan/Assigned
We have following columns in the report,
Plan: values which we plan in CJR2 or CJ40
Actual: comes from the Goods Receipt or Invoice
Commitment: Open PO value (for which we don't post GR)
Remaining Order Plan: ?
Assigned: ?
Available: Plan - (Actual + Commitment)
What is the equation for Remaining order plan and Assigned columns
Thank you
Hi,
Please go through SAP Note 922177 in order to understand Rem,OrderPln.value.
Regards,
SL
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
The "Remaining order plan value" is calculated like "planned costs" - "actual cost" - "commitments".
The "Assigned" column of a PS report is defined as the total of the columns "Actual", "Commitment" and "Residual order
plan"
Hope this clarify your query.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Refer SAP Help or search the forum. This has been discussed more than a couple of times in the forum.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.