Project Stock Commitment

0 Kudos

I created a project stock in relation to a WBS. However, upon viewing in CJI5 Display Project Commitment Line Items, the project stock did not reflect in the report. However, regular PRs are reflected in CJi5.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

CJI5 is used to see the commitments and not the Stock. Check MBBS for stock. You can also check MMBE.

Answers (3)

Answers (3)

0 Kudos

Thank you for the replies.

My add on to this thread: Can the PR amount be displayed in CJI5 with the PR containing Project Stock? That is the additional scenario we encountered.

.

Former Member
0 Kudos

yes, If PR is account assigned to WBS/Network. It will be visible in CJI5 report.

Regards,

Mahendra Dighe

Former Member
0 Kudos

Yes, it will be shown in CJI5 report.

Former Member
0 Kudos

Hi,

Those project stocks are shown on CJI3 & S_ALR_87013558 as statitical actuals(withing actual not separately) if that particular inventory GL account is crated as a statical costelement.

BR,

SL

stheurkar
Active Contributor
0 Kudos

Hi,

also you can see project stock by using transaction MB52. here you have to select special stock indicator Q. once report is executed then add wbse in layout.

Regards,

Sandeep