on 08-18-2011 5:49 PM
Dears
My material was activated with 01 inspection type
I didn't create any ispection plan for this materail
I have created a purchase order and done Goods receipt
now system created a inspection lot with status CRTD CHCR SPRQ
Now i need to assign a inspection plan manully to this lot
Please tell me how i can do that
Faisal
Hi Faisal,
Check the quality plan of the material in QP03 with valid date Lot size and status as release(usage5 and status 4), check deletion indicator.
Please reset the inspection lot go to QA02 assign the task list to lot and then have the status of the lot as REL and then do the UD.
Regards
Hari
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Check The Usage of the Task List. it should be 5.
Also check the status as released - 4
Thanks
Sachin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Faisal,
Refer this [Link|http://wiki.sdn.sap.com/wiki/display/PLM/InspectionlotswithCRTDstatus-Causesand+Remedies] also.
Regards,
AR
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Assuming that you have all the master data pre-reqs completed like Material Master QM view, Inspcetion Plan with the valid key date, Usage, Status etc....proceed as below
Go to the inspection lot under change mode.
Click Insp. Spec tab
Click Task List/spec tab.(This will assign the plan to the lot)
Click Sample tab and then click SAmple Calc icon to calculte the sample.
SAVE.
The relevant inspection plan will get assigned and your Inspection Lot will be in REL status.
Also, if you search the forum you will see a lot of threads related to this topic.
Naik
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
i try to clik task list specfication button in change inspection lot tab but system through the error like follow
-
No inspection plan could be found
Message no. QA278
Diagnosis
A task list could not be found for the selection criteria. The
inspection setup for this material in the quality management view of the
material master defines an inspection with a task list.
-
but i have a inspection plan already
Thanks in advance
Faisal
hi faisal,
1. First check ur usage and status for task list is 5, 4 respectivly.
2. Check same material is assigned to the inspection plan.
3. Check your date of lot cration which should always not before task list creation.
if these all conditions are met then definatly lt will be released, check and feel free to ask if still problem is not solved.