on 08-18-2011 12:54 PM
Dears
I have requirment as below
I need to have a common inspection plan in the system
So i dont want to create any inpection plan against material
when ever inspection lot was created is it possible to assign a common inspection plan
the thing is that i dont want to create more master data in the system
If it is possible please tell me how we can achive this
Thanks in advance
Faisal
Hi Faisal,
Instead of creating inspection plan for every material.
You can create one inspection plan and assign the same plan to all materials.
This can be done in the Material Assignment in QP02 transaction.
You can keep on adding materials day by day to this for the same group and group conuter.
If you want to create in mass, hope you can create a BDC
Refer the below link
http://help.sap.com/saphelp_46c/helpdata/en/8d/4103aff89511d283de0000e829fdb3/content.htm
Thanks and Regards
Hari
Edited by: Harikris_83 on Aug 18, 2011 5:56 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can have only one inspection plan and assign all materials to it. No problem. However, you need to confirm that this serves the QM purpose of your company/products. If it is OK- no problem.
In course of time, as new materials are created, you can assign them to this Inspection Plan.
I don't think you need any BDC for this. Simple Excel will serve your purpose - unless you have materials in thousands.
Regards, KrishnaM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.