Unable to deliver scheduling agreement

balaji_parsewar
Contributor
0 Kudos

Dear SD Gurus,

I am trying to deliver scheduling agreement. Details are as follows :

Rounding Qty - 10

Forecast Delivery schedule - 200 qty of current date.

Stock is available in required storage location.

While delivering, I am getting error message - "No schedule lines due for delivery up to the selected date."

I had tried by changing selection date i.e. keeping it in future also.

Please guide me with the probable corrections.

Regards,

Balaji Parsewar

Accepted Solutions (0)

Answers (2)

Answers (2)

Lakshmipathi
Active Contributor
0 Kudos

Double click on the material code in that scheduling agreement and in the first tab (I think it is Sales), you can see the first field Quantity on top. Check what is there.

G. Lakshmipathi

balaji_parsewar
Contributor
0 Kudos

Hi Sir,

After providing target quantity, I am able to

- Deliver

- PGI

- Bill

the above scheduling agreement. Thanks for the same.

Regards,

Balaji Parsewar

prasanna_kumar4
Active Contributor
0 Kudos

HI,

As for my Knowledge while you doing the scheduling agreement you need to assign on which date you are going to do the delivery and mention that delivery date

if it is normal check with schedule line category t-Code VOV6 whether you checked the Field "Item relevant for delivery "

Regards,

Prasanna