HI,
I have a case in which the particular SC has gone through the approval process and generated the PO no. which I am able to see through BBP_PD. Also there is no document mismatch or G/L account problem. But the SC status is "Error in Transmission". I tried to transfer the follow on document and update the SC backend data but then I got an alert in RZ20 which said "SG105 enter rate RMB/USD rate type M in the system settings" . Can any one tell me what does this imply and how to go about the error analysis.
Thanks in advance.
With Regards,
Rajesh
Hi Rajesh,
It seems to be an exchange rate issue.
Please check the rate conversion in your system.
Vendor currency vs PO currency ?
Kind regards,
Yann