on 08-17-2011 11:00 AM
Hi Experts,
I have maintained a planning calendar in SAP APO MAT1(T-code) for certain materials which will generate the purchase requisitions on every friday,but for 2 materials the Requisitions are getting generated on thursday.For the rest of the material its working fine.
I have checked the data,tlane etc but not able to get the root cause
Please help me in this...
Thanks,
Suyash
Edited by: suyashk on Aug 17, 2011 12:03 PM
Hi Suyash.
There are many possible reasons, most of which are listed in note
333386 Availability date different in APO and R/3
Please, check if the items in the note help you determine the reason for the difference.