CJ20N issue

Former Member
0 Kudos

Hi All,

While I am executing T code Cj20N and changed the status of WBS but when I try to save the same in CJ20N, it takes time then finally gives Time out error

Please help

Accepted Solutions (0)

Answers (1)

Answers (1)

stheurkar
Active Contributor
0 Kudos

Hi,

take help from your basis consultant.

Regards,

Sandeep

Former Member
0 Kudos

ok but they suggested to open a oss message

Former Member
0 Kudos

Then open an OSS message.

0 Kudos

Hi,

Please go through the SAP Note 206264 - 'Large project structures, long runtimes'. Compare your project with the guidelines. This may be one of the reason.

Former Member
0 Kudos

Ok Thanks