Dears

In my finished materials routing i have 6 operation and third operation is external operation

i need to make a inspection when material is coming to production plant

please tell me the details step to achive this

faisal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

When the marterial comes to plant, GR should be made for the purchase order of the external operation. The inspection lot will be of origin 01 and assigned to the inspection type which is specified in the operation of the production order. Therefore, properties and attributes of this inspection will be decided by this inspection type. This inspection is only related to the external operation and no stock posting takes place. Real GR will be done when the production order will be delivered.

Regards.