on 08-16-2011 9:08 AM
Hi,
I am facing one problem in default actual project progress method.
I assigned default method in SPRO node of PS,Progress Analysis ---Define Measurement Method as Default Value
Internal processing activity plan = method :0000000001
Internal processing activity actual = method :0000000006
But when I run CNE1 :progress determination system by default taking method 0000000001 for both plan & actual.
When I manually entered in internal activity, measuring method :0000000006 then system calculate correct progress.
Why system is not considering configured default method for internal activity actual ?
What will be the reason?
Regards,
ASP
i will try some exit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
It is not possible to default in the project, at least you need to maintain the progress version in each activity. May be you can check some BDC option.
There are many threads earlier discussing similar cases, please refer them.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
98 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.