on 08-15-2011 3:39 PM
We were applying some security notes in the SAP ECC6 Ehp1 system however, we forgot to implement a pre-requisite which was an external transport before implementing a note (in dev. we did it right but in test system, we forgot to do the external import first). Due to this, the RDDIMPDP job is getting cancelled every time & we get dumps whenever we use SE01 or SE09 or SE10.
Pre-requisite note : 1497003
Next note : 1582138
Could you please help resolving this issue ?
Thank you !
Hi,
You can de-implement 1582138 and start afresh by applying the changes in the pre-requisite note.
Regards,
Hari Kishan
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can try with resetting note implementation in dev system which will generate one transport request. And move this transport request to test system as a result note will be reset in quality system as well.
Then again implement note in dev and transport it to test system after implementing pre-requisite note.
Thanks
Sunny
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you may de-implement note 1582138 directly in test system with opening system(SE06) & client SCC4. after this
you can implement both the notes in correct sequence directly in test system. or
you de-implement both notes in dev, collect changes in transport(discard) and later implement both and move transprt.
thanks
ashish
User | Count |
---|---|
78 | |
9 | |
9 | |
7 | |
7 | |
6 | |
6 | |
5 | |
5 | |
4 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.