Hi Gurus,

I created appropriation request using IMA11. I put start date and completion date in IMA11.

After it, I went to CJ20N to tick billing elements and Acc Assignment, enter settlement rule and then release the WBS. (I did not put any basic start date and end date at this stage).

When I run CN43N, the start date and end date in IMA11 did not show in the report.

Is there any way I can pull the data? or any other report I should run?

cheers,

GIM

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Check out the reports under the Master Data Lists like IMR4 - 7.

Regards

Sreekanth

Former Member
0 Kudos

Hi, Sreekanth

Thanks for the info. I run the report. It gave me the Impletmetation start dates. However there are no completion date in the report.

Is there any way to pull that data in?

GIM

Former Member
0 Kudos

Hi,

Is the Completion Date a user field? If yes, in the reports you have an option to choose fields and bring all the user fields in.

Regards

Sreekanth