on 08-15-2011 2:02 PM
Hi Gurus,
I created appropriation request using IMA11. I put start date and completion date in IMA11.
After it, I went to CJ20N to tick billing elements and Acc Assignment, enter settlement rule and then release the WBS. (I did not put any basic start date and end date at this stage).
When I run CN43N, the start date and end date in IMA11 did not show in the report.
Is there any way I can pull the data? or any other report I should run?
cheers,
GIM
Hi,
Check out the reports under the Master Data Lists like IMR4 - 7.
Regards
Sreekanth