Hi Experts,
Are there any ways to rescheduling on partially confirmed operations in APO DS planning board?
Customer using Heuristic Profile SAP001 in APO, and now only those planned/production orders which have not yet started confirmation from R3 is possible for rescheduling/drag and drop in DS planning board.
During debugging, I found that when executing procedure "APS_ACT_SCHEDULE" in function module /SAPAPO/OM_ACT_SCHEDULE, the capacity requirements could not be selected for partially confirmed operations, it then cause rescheduling on partially confirmed operations failed.
Thanks for reply.
Best regards,
Cherry
Hi Cherry,
you have to interrupt the operation, then you will be able to reschedule it. Interruption can be done interactively in the DS board by right click on the operation or via function call "Interrupt Operation" in the backgroud planning run.
Best regards
Thomas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Thomas,
Thanks for your valuable response.
By using "Interrupt" functionality in DS board, the partially confirmed operations can be rescheduled, but when you double click on this operation, you will see the checkbox "Part.Conf." is removed.
Now customer want to see this flag stays to be set, so as to configure the color for this partial confirmed operation, and meanwhile to enable the rescheduling functionality.
Is it possible? Any enhancement we have to do for this requirement?
Looking forward to your reply.
Best regards,
Cherry