i have two activities like act 1 and act 2, act 2 can only start after act 1 get completed. but system is allowing me to confirm act 2 before act 1. how can i restrict the act 2 to be confirmed before act 1.
Please create a validation by using user exit.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This may not be possible in standard SAP. Please use enhacements in confirmation. you can find them in customizing for confirmation--> enhancements for Confirmation.
There are a couple of enhacements like CONFPS02, CONFPS03,CONFPS04,CONFPS05.Please take help from your ABAP team.
Warm regards,
Srinivas Potluri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
99 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.