PPDS extraction of an operations setup time

Former Member
0 Kudos

I have a requirement to extract the duration of the setup activity for a PPDS operation. Using the standard datasource I can get the overall setup time for an order from the Orders datasource, however the operations datasource does not have the setup time seperate from the operation duration.

I require this as I need to know the activity times for operations by resource - order level is not detailed enough

can someone tell me how I can get this information?

Thanks in advance,

R

Accepted Solutions (0)

Answers (1)

Answers (1)

tiago_furlanetto
Product and Topic Expert
Product and Topic Expert
0 Kudos

You should be able to achieve this with BAPI BAPI_MOSRVAPS_GETLIST2.

Former Member
0 Kudos

I was ideally hoping for a BW datasource solution but the BAPI will provide the data, I presume this is the only way?

Thanks,

Richard