on 08-11-2011 9:49 AM
Hi,
I have a Client requirement in which they want to make changes to Budget on the whole.
Suppose, there are 200 WBS elements, the requirement is that the Budget has to be changed completely for all the WBS elements.
E.g., Initial Budget Rs.250 for 200 Wbs elements
Now, there is a change in the budget as Rs.350.
For all the WBS elements value should be changed at a stretch.
Thanks,
S.Raghavan
Not possible through Mass Change. Try BDC.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Did you try Transaction : IMCBR3 - Mass Release of Budget for Projects ?
Thanks
abdul.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
When you say 200 WBSE then do they belong to the same project or are they seperate projects? If they are the same project then within CJ30 you may use editing functions to increase the budget based on %. In case they are seperate projects then I'm afraid this will not be possible (except for the LSMW etc.). Have you tried using Investment Management module, this may help perform the same function on seperate projects belonging to the same IM Program (do check that out).
Also is it possible for you to change the cost plan and upload/change budget via copy view?
Regards,
Syed Ammar Zaheer
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can also have an LSMW written and load the file.
Regards
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
110 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.