on 08-10-2011 9:56 PM
Hi Friends,
This is my scenario. Our requirement is to budget in transaction currency. I have a US company code project where I do the budget in GBP and all activity ( PO) are planned in GBP too.
My Tolerance setting is error at 100%. Settings in Budget profile is Budget in T.Curr.
I have a 1000 GBP budget and equivalent Obj.Curr. is 1500 USD based on my P rate. Means I should be able to plan 1000 GBP at my activity level ( external activity) . But system not allowing it. I am able to assign 1500 USD at NWA and Save.. not the 1000 GBP.
Anyone came across budget with T.Curr. and Availability control?
Hi,
In the budget profile, you have an option to do the availabilty check with respect to "Object Currency". Try this one and also check if you are using a different exchange rate type in the budget profile.
Regards
Sreekanth
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I am not aware of having the availability check in transaction currency. But as far as the cost assignmnet, you should be able to plan 1000 GBP. Check in OKEQ, for your version the value date setting for the fiscal year. Make sure it pointing to the correct date so hat system picks the latest appropriate rate while doing planning.
Regards
Sreekanth
User | Count |
---|---|
99 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.