Dears

For a finished goods i have two activities

First activity is form PP side

and second activity from QM side

So i create a production order hence i got inspection lot

I confirmed the first activity by CO11N

Now QM inspection is rejected the during usage decision

Even though QM usage decision is negative system allowing to confirm the second actvity

Is it possible to block the second activity confirmation

Pls help

Faisal

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

User exit CONF0001 Enhancements in order confirmation