on 08-10-2011 1:39 PM
Hi,
We have been trying to define working shifts/ cutoff for shipping points. While scheduling SAP is using the user time zone to calculate the MAD time, GI time etc. I need it to use a specific time zone that I define and not the time zone of the user processing the document. There is a field for time zone at the point where we allocate the shift definition to the calendar but it is not working. Is there anyway to achieve this ?
Thanks,
Hari.
SAP note 1629695 solved the issue .
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks for all the replies. I am already using work shifts and getting confirmations down to the minute. But my issue is that the GI,MAD time etc are being calculated according to the time zone of the user processing the document and not in accordance to the plant/shipping point or the time zone that I attached to the time stream . This does not make sense as we may have an intercompany order being created by the buyer who is in a different time zone and the date/time gor GI should be based on the time zone of the shipping point.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI,
You can maintaining a factory calendar with precise scheduling for the shipping point.In the precise scheduling the working hours can be maintained upto minutes level.
Regards
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Hari...
Try factory calender for shipping point...
Thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.