on 08-10-2011 10:28 AM
Dear All PS Gurus,
We have specific requirement to track Budget in PS ( WBS Level ) thru material qty as well as value.
Are there any work arounds or any other solutions..
Umesh Bagul
Hi,
As rightly mentioned by Gokul, Budgeting on the quantity is not possible in Standard SAP. The only to get through this is to go for a Z development. Create a Z table and plan all the required material & quantity against each project. During the PR/PO or stock issue , validate the quantities with respect to the quantities entered in the Z table.
Warm regards,
Srinivas Potluri
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Surely it will require Z development.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
This is not possible in the standard system. I am not aware of any other work around. However, you can search the forum as i guess this was discussed some time back in the forum.
Regards,
Gokul
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.