how to transfer PDS from ECC to APO?

Former Member
0 Kudos

HI

Could anybody tell me how to transfer the PDS from ECC to APO?

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member187488
Active Contributor
0 Kudos

Hello,

To transfer PDS to APO, you must have planning versions at ECC side, which are defined in material master, MRP4 tab.

Then create an integration model in CFM1 (or use existed) to include 'PDS' in the model.

As you can see, there're several types of PDS, choose the one you need.

Then just activate the integration model in CFM2.

At APO side, you can use /sapapo/curto_simu to view the PDSs.

Please notice that unlike PPM, you cannot make changes to PDS in APO system.

Best Regards,

Ada

Former Member
0 Kudos

Hi,

You need to Cif the PV from ECC to APO as PDS ( either PPDS PDS or SNP PDS) in tcode CFM1

1. Generate the integration model in cfm1.

2.Activate the integration model in cfm2

http://help.sap.com/saphelp_scm70/helpdata/en/4d/01be3d1abbe913e10000000a114084/frameset.htm

Thanks,

nandha

abhay_kapase
Active Participant
0 Kudos

Hi Lauliu,

Create a Integration model (CFM1) for type PDS and give what type of PDS you want to transfer. give the production version which you must have mentioned in MRP4 view of material master.

Activate integration model (CFM2)

Regards,

Abhay Kapase