Error while uploading MSP project into SAP PS

Former Member
0 Kudos

Dear Friend's,

For uploading MSP project into SAP PS we are using openps4MSP version 4.0 & MSP version 2007. incase of SAP PS to MSP downloading is ok.

While uploading we are getting following error. Also I have gone through relevant notes on MSP PS interface still I am unable to understand what exactly is the missing.

Action log is as follows.

The WBS.Maintain BAPI was called.

- duration in sec.:0.109396699997887

- return code: E

- I CJ546 WBS-Dates Create

Start date is in the past

- object ID: B1101501000000000 /

- I CJ546 WBS-Dates Create

Start date is in the past

- object ID: B1101500000000000 /

- E CN009 NetworkActivity Create

Network 4003941 does not exist

- object ID: 0000040039410010 /

- E CN009 NetworkActivity Create

Network 4003941 does not exist

- object ID: 0000040039410020 /

- E CJ280 NetworkActivity Create

Termination: Too many errors (more than 10% of methods)

- object ID: 0000040039410020 /

ERROR test import into PS system failed

ERROR updating PS project

Thanks & Regards,

Suvin

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Dear Customer,

Regarding error 5message CN009, could you please review notes 542887, 445323? For Error Message CJ 280, could you please review notes 1154501 and 458977?

Kind regards,

Enrique

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

Which type of scheduling setting have you configured for WBS scheduling and for n/w. ?

Also, download calendar from SAP to MSP and then add column 'Task Calendar' in which select the downloaded calendar.

Check SAP NOTE 579761

Regards,

Harsh.

Edited by: Harsh Saxena on Aug 10, 2011 3:18 PM