on 08-10-2011 2:51 AM
hi gurus,
my issue is, whenever i change the process order dates in ecc(the date is changed to date that is outside my planning horizon) they dont show in the APO and instead the APO is overriding the changes to the original date.
can u guys help in resolving this issue.
thanks in advance
regards
maddy
Hi Maddy.
As APO is the leading system in scheduling, the dates defined in ECC might not be retained after the order is sent over to APO. You can take a look at note
684356 Date transfer between R/3 and APO
for details.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Check the settings defined in /SAPAPO/CP3 for inhouse production orders.
Thanks,
nandha
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
8 | |
4 | |
3 | |
2 | |
2 | |
1 | |
1 | |
1 | |
1 | |
1 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.