SRM attachments transferred to ECC?

Former Member
0 Kudos

Hi all,

Can anyone confirm if the attachment from PO in SRM(ECS) are replicated to ECC PO with SRM 7.0 EHP1?

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi CG,

Yes it is transferred using BADI BBP_CREATE_BE_PO_NEW.

Regards,

Cruiser

Former Member
0 Kudos

Thanks.

But I had read in one of the posts that it was a std functionlity with SRM 7.

We are upgrading our system form 5.0 to 7.0.1 and dont intend to implement any custom solution for attachment transfer from SRM PO to ECC PO.

Former Member
0 Kudos

Hi,

It should be a standard functionality. If your backend ECC system is on ECC 6 enhancement pack 4 or higher, the transfer of attachment to backend system from SAP SRM system is standard one.

Thanks and regards,

Ranjan

Ranjan Sutradhar

Former Member
0 Kudos

Thanks Ranjan.

But is the tarnsfer of attachments standard for "Extended classic" scenario?

Former Member
0 Kudos

Hi Experts,

I have a similar requirement for transferring attachments from SRM PO to ECC PO in SRM 7.01.

Can anyone confirm if this is possible and if so,what are the solution steps?