One of my semifinished material i have routing with two operation from PP side . I add a new
operation for QM inspection with Assign QM work center and assign inspection chracterestic in routing
Now i have the following dout on this
1.What is the first process ,wether PP guy need confirmation first or QM guy need do inspection first?
2.While i try to do UD system showing a warning message :Assigned order 1000054 is neither completed
confirmed...i have done all confirmation already
3.As i assigned a new operation with control key QM04.Now pp guy need to confirm this operation also?
thanks in advance
Faisal
In simple words ,The person confirming the first two operation should also confirm the last one irrespective of control key.
.Generally quality person do not have authorization of operation wise confirmation .
Do operation wise confirmation & post material document against order in MB31.
This will ans all your question.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Faisal,
How did you confirm the operations? Through CO11N? Can you just check the status of production order in CO03?
Hopefully you need to click on final confirmation in CO11N operation wise. Order status should have status as CNF or TECO in order to disappear the message you are getting.
All above, since this is an information message you can still go for UD. Since 03 lot doesnu2019t have stock posting facility this will not have any adverse costing effects.
Regards,
AR
User | Count |
---|---|
99 | |
9 | |
9 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.