Schedule Line Category.....

Hi Experts,

I am working on a 3rd Party scenario where client do not want to have NB doc type for PR instead they have a customized doc type as ZZ which they want us to maintain in the schedule line cat...

Besides the 3rd party scenario here we follow is quite different means at schedule line cat level we have 601 mov type and Pur req del scheduling is also checked so that in the system we receive goods and do PGI but physically its been delivered by Vendor this is what I understood by seeing the settings....

My question is after copying CS and renaming it as ZS and if I try assigning ZZ PR doc type an error msg crops up"goods movement not possible for third party schedule lines".......why is that error am facing?....

Also can anyone suggest me how to circumvent this issue?....

If its not possible then how in the std CS schedule line cat 601 mov type is maintained?......

Thanks in advance....

replied

Hi,

Can you please tel me in that CS Schedule Line

1. what is mentioned in the Item category Field " 5 or 0"

2. What is mentioned in the Acct Assignment Category " M or X"

Please clarify

Regards,

Prasanna

0 View this answer in context