cancel
Showing results for 
Search instead for 
Did you mean: 

Planned time & Planned date in TR

Former Member
0 Kudos

Hi Experts,

Can you please tell me why the planned time is always showing 23:59:59 in TR? and Planned date in TR is defaulting the creation date, where as planned time is defaulting to 23:59:59.

Thanks

Srinivas

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

How are you creating the TR? On the initial screen in LT01, the default is 23:59:59 but it can be changed here. If you are copying from a PP order, please see SAP note 97113. If creating the TR from a material movement, a default time of 23:59:59 is copied in.

Hope this helps. Regards,

Sinéad Curran